Middletown roads: 7 streets to be paved this fall

Middletown will be paving several streets this fall.

The city has contracted with John R. Jurgensen Company to pave the following streets:

  • Central Avenue between Breiel Boulevard and Marshall Road.
  • South Main Street between 11th Avenue and 18th Avenue
  • Kensington Street between Central Avenue and Grand Avenue
  • Wicklow Drive between Limerick Lane and Cambridge Drive
  • Limerick Lane (all)
  • Poppy Drive (all)
  • South Heinkel Road between Poppy Drive and Central Avenue

Concrete repairs are now underway and paving should start in a few weeks, according to Scott Tadych, city public works director.

The paving projects are scheduled to be completed by mid-November, he said.

The total cost of the project is nearly $1.75 million and includes an $850,000 grant from the Ohio Public Works Commission.