ODOT will spend another $16.4 million on 10 other projects in Clark County this year.
Here are three more top Clark County projects and when they are scheduled to be completed:
Ohio 41, East of Springfield to Ridge Road; U.S. 68, Interstate 70 north to the county line
Project description: Smooth seal resurfacing
Cost: $6.24 million
Estimated completion: August 2018
Interstate 70 at Interstate 675
Project description: Deck replacement
Cost: $5.7 million
Estimated completion: October 2018
Ohio 41
Project description: Culvert replacements
Cost: $747,487
Estimated completion: September 2018
This year, 88 projects costing $142 million are scheduled to start in District 7 which includes Auglaize, Champaign, Clark, Darke, Logan, Mercer, Miami, Montgomery and Shelby counties. In all, ODOT will spend about $2.35 billion on 959 projects across the state, 28 considered major, officials said.